Update on Mooloolaba Seawall progress, as below from the council. ⤵️
* November construction update *
October has seen significant progress across the Central Meeting Place, with crews continuing work on the terraced seawall and public spaces despite recent wet weather.
Construction of the beach access stairs, all-abilities beach access ramp and additional landscaping along the seawall continues to advance.
Four sets of beach access stairs will be constructed within the seawall over the coming months. They will provide access to the beach and terraces and be progressively opened as construction continues. Images below show beach access stairs and all-abilities beach access ramp.
In the meantime, beach access remains available via the ramps on either side of the Surf Club tower.
North of the surf club, construction includes sandblasting of the seawall terraces and steps, planter box installation, continuation of all-abilities beach access ramp and ocean viewing deck. The image below also shows stone facing works on the vertical seawall section.
Major construction for the overall Stage Two project remains on track for completion in March 2027, weather and site conditions permitting.
* November works *
Continued construction of the terraced seawall, all-abilities beach access ramp, ocean viewing deck and seawall planter boxes.
Ongoing stone facing works to the vertical seawall section
Continuation of concrete works for the road realignment and pedestrian crossings in front of Syrenuse and Zanzibar buildings
Paving works along new road edge in front of Peninsular Building
Continuation of underground electrical and plumbing works
Fit-out and carpentry works for the new public amenities with all three ‘pods’ under construction
Footpath and turf preparation between Surf Club and existing BBQ area.
* Reminder — External agency works *
Energex electricity network upgrades
Due to recent wet weather, Energex's planned underground electricity infrastructure upgrades and associated pit rebuild works (adjacent to Augello's) are now expected to start on Monday night, 2 November. The upgrade works will support improved capacity and reliability of the local electricity network.
To minimise impacts on businesses, residents, visitors and traffic, most works will be night works and undertaken between 9pm and 5am, weather and site conditions permitting.
Marine Safety Queensland beach nourishment works
Queensland Government Marine Safety Queensland is dredging sand from the Mooloolah River mouth to help maintain safe boating access. Works are expected to take place through November, weather and swell conditions permitting. The sand is being placed south of the Mooloolaba Surf Club to help strengthen the beach and improve protection against future storm events.
* Christmas and New Year period *
Construction shutdown – 18 December to 3 January (inclusive)
Construction activities will pause over the peak holiday season.
More information will be provided in the December update.