03/12/2024
Early 2024 we were engaged to replace Sand and Cement render on this Grade II listed property in Abingdon.
Underneath we found the most rotten timber frame I've seen in over 40 years in this industry. The degradation of the original frame was so bad the the entire gable end of the house required shoring up.
In the last few months we have had to stabilise the building, survey the remaining frame and then rebuild, rescuing and reusing as much of the original framework as possible.
We are now after months of painstaking work nearly finishing the restoration of the framework.
Once finished we will be insulating the wall with a breathable insulation, applying a breathable membrane, counter battening and then applying 100's of oak lath, before closing it up for the winter, ready for lime rendering in the spring.
A real labour of love this one!