10/11/2019
Week 07- 12 October
Our plumber finished pipe work for cold and hot water system, tested them and found no leaks. We were now able to start on the bathrooms, as well as closing up floors and walls. However, we still did not have the final drawings from the architect for the bathroom layouts – she said we worked too fast and she could not get the drawings done in time! Plastering is still in progress and will be finished soon.
Originally it was estimated that this project would be completed by the middle of January 2020, but after five weeks we had done over 50% of the work. The client had rented a house for four months, but as the work has progressed much faster than expected, he will be able to move back home approximately 6 weeks earlier than initially planned.