18/10/2025
Been another busy couple of weeks at our large project in east grinstead. 130 metres of new drainage system being installed, new proposed patio areas being prepared, dug out, ready for MOT. We have the fibre and power cables laid in a 150 metre trench up to the new gate entry. On one side of the house a large 12 unit soak away has been completed. 100 metres of land drain being dug, installed ready to pick up the new rain water catchment on the other side. The digger has been busy !! 👷♂️ well done lads !! Also our new plant room has taken shape with the tanking team finishing the membrane system, let’s get the screed down!