Walter Crescent Renovations

Walter Crescent Renovations A timeline of the renovations for Walter Crescent. Start Date: 13 January 2020

Master bedroom, a few finishing touches remain but we have moved in.
07/11/2023

Master bedroom, a few finishing touches remain but we have moved in.

Tiling take two... also floors were finished a few weekends ago....so close to being finished internally now...
12/10/2023

Tiling take two... also floors were finished a few weekends ago....so close to being finished internally now...

Flooring progress after the weekend. Just need one more day to finish it off.
25/09/2023

Flooring progress after the weekend. Just need one more day to finish it off.

Flooring day for master-suite, practice run to check gaps at end is calc nicely.
23/09/2023

Flooring day for master-suite, practice run to check gaps at end is calc nicely.

Painting almost completed in master bedroom. One more coat of aqua to go. Major issues with the tiles though...so we are...
20/08/2023

Painting almost completed in master bedroom. One more coat of aqua to go. Major issues with the tiles though...so we are at a stand still with that unfortunately. Also vanity is installed. Smart Living Constructions Holloway Brothers

Plastering and waterproofing completed. Tiling has started :)
15/08/2023

Plastering and waterproofing completed. Tiling has started :)

Plastering and rendering today. Smart Living Constructions
07/08/2023

Plastering and rendering today. Smart Living Constructions

More linings going in. Smart Living Constructions
01/08/2023

More linings going in. Smart Living Constructions

Wall linings have started including insulation...will take shape quickly now. Smart Living Constructions
31/07/2023

Wall linings have started including insulation...will take shape quickly now. Smart Living Constructions

Starting to look like it's part of the house again. Smart Living Constructions
25/07/2023

Starting to look like it's part of the house again. Smart Living Constructions

Starting to look like a house again.....even if it is made of foam! Smart Living Constructions
11/07/2023

Starting to look like a house again.....even if it is made of foam! Smart Living Constructions

New master bdrm & ensuite framing almost done, windows in. Smart Living Constructions
02/07/2023

New master bdrm & ensuite framing almost done, windows in. Smart Living Constructions