29/06/2021
A great day to be working in Dorrigo with the team. These images show the progression from pouring a slab through to framing. Preparation for the pour including concrete block footings takes about 2-3 weeks, with the pouring of the slab taking only one day. The concrete is pumped and placed with a team of men, screeded, and finished with a power trowel machine (helicopter). Frames are built in the factory and erected on site and take about 2-3 weeks, depending on the complexity of the job.