07/09/2024
Great to see AJT Crack Mat being utilized on this project!
https://www.facebook.com/share/gLLSBXFZU8zFMpaD/?mibextid=QwDbR1
From Friday 6 September 2024, Gold Coast–Springbrook Road between Neranwood and Springbrook will return to 2 lanes.
This marks the completion of major restoration works on this road, after multiple sections were significantly damaged by extreme rainfall and flooding events in 2022 and late 2023.
At this section of road, work crews have installed close to 260m of concrete-lined drainage to direct the flow and run-off of water.
The recovery works are jointly funded by the Australian and Queensland Governments through the Disaster Recovery Funding Arrangements (DRFA). https://brnw.ch/21wMoIh
From November 2024, roadworks to improve the resilience of Gold Coast–Springbrook Road are expected to commence. For the latest traffic and travel information visit to the QLDTraffic website: https://brnw.ch/21wMoIi or download the app https://brnw.ch/21wMoIg
We thank the community for their support and patience during these important disaster recovery works.