09/28/2025
We quoted on this job back in January, didn’t get it for whatever reason. Can’t win em all… then I get a message two weeks ago that they still needed 2 showers done as the previous guy “didn’t work out”. Long story short, there was 3 shower stalls to be done, first guy got one done in 4 months, started the second one and was let go. We tore out the regular drywall he had put in, replaced with glasroc tile board, installed a mud bed and tiled shower 2, then it was a complete tear out of shower 3 and refinish. Job completed in about 9.5 days and the customer is happy! I used to work here some 20 years ago.