30/05/2026
Week 4 on site for this new extension in Uddingston.
Steelwork in, timber kit up, roof on, and the main structural opening steel installed shortly after these photos were taken. Next big step will be the doors and glazing from in the next couple of weeks.
This visit was also to review the contractor’s valuation before certifying the next payment by interim certificate.
That’s part of our role when we’re providing Contract Administration. Not just popping out to site for a look, but checking progress, reviewing what has been claimed, and making sure payments are certified properly as the build moves on.
Good progress from