Here are 20 photos of the construction of our Grade-II listed flat project in Queen’s Gate ahead of its completion this spring.
These photographs show key moments of the renovation in reverse chronological order from week 28 to the start of construction.
We’ll publish photos of the completed project soon.
1. Week 28 - Gradual completion of the living room
2. Week 28 - Completion of gilding and decoration
3. Week 27 - Gilding of cornices
4. Week 25 - Installation of the kitchen
5. Week 25 - Installation of new storage units
6. Week 21 - Installation of double-glazed timber sash windows
7. Week 20 - Laying an oak parquet on the acoustic subfloor
8. Week 16 - Plastering and repair of historic ceilings
9. Week 10 - Running of wires and pipes under a future acoustic floor
10. Week 10 - Casting of a reinforced concrete jacket around a brick pier
11. Week 8 - Wiring for a future living room chandelier
12. Week 8 - Recreation of the plant room floor
13. Week 7 - Demolition of the plant room’s floor
14. Week 5 - Raising the entrance steel beam
15. Week 4 - Pinning a brick wall in preparation for raising a steel beam
16. Week 3 - Revealing the historic ceilings
17. Week 2 - Opening the historic archway between the front and rear rooms
18. Before construction - Discovery of a historic ceiling above a false ceiling
19. Before construction - A kitchen without natural light or air extraction
20. Before construction - An archway blocked by a non-historic wall
All photographs © Jflemay Architecture and Design RIBA, 2026