03/05/2026
Westbrook House progressing well.
Blockwork now up to roof plate,
single-storey extension structure complete, and hip-to-gable timber framework in place.
Next phase: install roof lanterns to the flat roof, strip the main roof, then felt, batten and complete a full re-tile.