21/09/2022
Day two of our latest kitchen fit out
Today in consultation with the structural engineer, we have significantly altered the proposed method of support.
The solution did involve two steel beams, upon exposing the full structure we are now utilising a timber solution. This saves a week wait for the steels to be fabricated.
Today:
✅ - Consulted at length with structural engineer
✅ - Completed procurement to the new timber specification
✅ - Built a C24 graded timber structural stud wall
✅ - Exposed lintel above main kitchen window to confirm structurally sound
✅ - Stripped artex & render from now removed pantry
✅ - Plumbing tidy up & first fix
✅ - Meet Electrician to confirm layout for Electrical first fix
✅ - Completed small remaining strip out tasks
Up Next:
🔜 - Electrical first fix for power & lighting
🔜 - Installation of structural timbers
Coming Next Week:
🔜 - Brick & Block work
🔜 - Floor Prep
🔜 - Lower ceiling
🔜 - Tacking
🔜 - Plastering