Jay Vee's Flooring

Jay Vee's Flooring Shop at Home Floorcovering Consultant & Project Manger

My last physical install last fall with bad hip , bad knees, but a big desire.
03/20/2026

My last physical install last fall with bad hip , bad knees, but a big desire.

What’s under here.
03/20/2026

What’s under here.

The plan for hip Surgery in March, gotta get play list lined up, news notifications shut off and life should be good.
01/30/2026

The plan for hip Surgery in March, gotta get play list lined up, news notifications shut off and life should be good.

Carol and I on our first New Years Eve together. Boston Park Plaza with the Fat City Band Praying for a calmer peaceful ...
01/01/2026

Carol and I on our first New Years Eve together. Boston Park Plaza with the Fat City Band

Praying for a calmer peaceful 2026 and good ridence to 2025 a disaster year.

Ran across this in Christmas decorations.  It reminded me I used to sent these out to some loyal accounts I worked with....
12/24/2025

Ran across this in Christmas decorations. It reminded me I used to sent these out to some loyal accounts I worked with. Customized cookie tins for Christmas.

Merry Christmas.

Reworked contaminated substrate
11/16/2025

Reworked contaminated substrate

Always cleaning up behind other trades.On this project, asbestos abatement was poorly executed. Abatement crews had to r...
06/06/2025

Always cleaning up behind other trades.

On this project, asbestos abatement was poorly executed. Abatement crews had to return after failing state air quality tests, and residual adhesive was left behind, requiring additional rework. Once I received clearance, I conducted thorough pre-installation testing and proceeded with the flooring installation.

Five years later, I received a call indicating tiles were lifting, seemingly without any adhesive present. Fortunately, I had documented all moisture and pH testing in compliance with ASTM F710 protocols.

Ultimately, core sampling revealed that the abatement crews had used a soybean-based adhesive remover during their rework. Over time, residual soybean remover migrated upward through the concrete capillaries, deteriorating the adhesive and causing the floor failure.

Thankfully, my thorough pre-installation data and prior experience with a similar situation at another school—where I’d personally observed soybean-based adhesive remover being used—enabled me to identify the issue promptly.

Experience truly makes the difference.

This one was fun, removed carpet and pad to install a Raskin LVP dry back floor  We raised subfloor to meet ceramic tile...
06/03/2025

This one was fun, removed carpet and pad to install a Raskin LVP dry back floor We raised subfloor to meet ceramic tile so we could skim coat CT make all on floor. Came out great

How about prepping the floor properly. The telegraphing subfloor voids manufacter’s warranties.
02/26/2025

How about prepping the floor properly. The telegraphing subfloor voids manufacter’s warranties.

01/29/2025

Address

189 Durfee Street
Fall River, MA
02720

Alerts

Be the first to know and let us send you an email when Jay Vee's Flooring posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Business

Send a message to Jay Vee's Flooring:

Share