09/04/2026
It’s into our 3rd week into the Lafayette commercial project.
We removed 1400 sq feet of glue down carpet.
Patch several several drywall holes.
Got the computer cables and power feeds cleaned up and hidden to give a better office look.
Got the two smaller rooms painted the new gray color plus hallway.
1 conference room has its Ceiling painted its first coat.
2 conference room started trimming around things.
Hopefully get more painting done this weekend.
Updates on more completed….