07/02/2026
Progress is continuing across all of our active projects! 🚧
📍 West Hartford
Exterior finishes are nearly complete, while interior trim work continues to move forward. Building 5 has completed toilet and water heater installations, with kitchens and vanities continuing to take shape. In Building 6, painting is wrapping up and flooring installation is set to begin.
📍 Avon
Framing has reached the final floor, and our plumbing team is right behind, installing DWV and water piping to keep the project moving on schedule.
📍 New Haven
Exciting progress at this future adult education center! Underground utilities are complete, framing is wrapping up, and we've begun the plumbing rough-in. Once finished, the facility will feature 21 bathrooms and a commercial teaching kitchen, creating a hands-on learning environment for future students.
Every milestone brings these projects one step closer to completion. We're proud to be part of building spaces that will serve our communities for years to come.