06/23/2026
This past week we have been working on a custom cabin build.
First, we added a concrete apron on an existing garage.
Then we got right to work digging the foundation for a slab on grade cabin, setting foundation forms/foam, roughing in all of the plumbing with Longhorn Plumbing, installing in floor heat tubing, and getting ready to pour their concrete floor.
There is a lot of work that needs to happen before we can even schedule pour day, but this one is ready to go!