04/24/2026
Quick progress update on this ADU project 👇
We had a short pause while we worked through some things with SDGE. After running load calculations, the original panel location we had planned wouldn’t pass with the existing infrastructure.
We went back, did additional calculations, and tested using the transformer pole at the front of the property — that option passed. So we relocated the 3-in-1, 400-amp panel to the front of the home to tie into that source.
Since then, we’ve passed inspection on the electrical service meter, plumbing, framing, and electrical ✅
Now it’s full speed ahead to finish this ADU. Stay tuned for the final stages — we’re back to posting regularly.