In this video we’re installing ceiling drywall. One thing you’ll notice is that there is no insulation installed yet — and that’s intentional.
This project will use blown-in insulation, which is a loose-fill product designed to create a consistent thermal barrier across the attic. We wait to install this type of insulation until after recessed lighting and other ceiling penetrations are completed.
If insulation is installed too early, it often has to be moved, disturbed, or even removed to run wiring and set fixtures — which can reduce its effectiveness and create unnecessary mess and labor.
By sequencing the work properly, we help ensure:
✅ Full insulation coverage with fewer voids
✅ Cleaner installation process
✅ Better long-term energy performance
Progress is moving along well — more updates coming soon as we keep pushing this duplex toward completion.